17-05-2024
Interflow have been engaged by council to conduct Sewer Mains Cleaning and Condition Assessing. These works will assist council with maintaining sewer assets and to improve the health and wellbeing of the community. Works will start on Tuesday the 21st of May in Crookwell and Gunning. It is anticipated works will be completed by the end of May. It is recommended that toilet seats are left closed for this period with a small weight such as a phone book left on lid to prevent toilet spirts. Interflow may need to access sewer chambers in properties and residents with these will be notified if access is required to these chambers.
Areas that are part of this scope are:
Crookwell:
Wade Street – Eastern end
Cowper Lane – Eastern end
Denison Lane – Eastern end
Denison Street – Eastern end
East Street
Robertson Lane – Eastern end
Colyer Street – Wade to Goulburn Street
Goulburn Lane – From Colyer Street to Roberts Lane
Gunning:
Yass Street Southern side from Nelanglo to Gundaroo Street