The following are roadworks commenced, completed or continued in the week ending 15 February 2024, and those which were scheduled for the week ending 23 February 2024.
Week ending Friday 15 February 2024:
Construction Crew:
Dalton Rd Rehab – Roadside drainage, culvert replacement, shoulder widening & gravelling.
Wheeo Rd final trimming for sealing next week
Gravel resheeting Currans Road
Maintenance Grading Crew:
MR241, Ladevale Road – Maintenance grading & maintenance gravel patching.
Rocklodge Road – Maintenance Grading.
Maintenance Crew:
Sheldrick’s Lane – Drainage.
Dalton/Jerrawa Road – Shoulder restoration.
Ladevale Road, Dalton/Jerrawa Road, Jerrawa/Hwy Road – Tar patching.
Concrete/Bridge Crew and Drainage Crew:
Shoulder repairs and storm damage Kangaloolah Road
Week ending Friday 23 February 2024:
Construction crews:
Dalton Road Rehab – Gravelling
Wheeo Road seal prep and starting Woodhouselee Road construction
Peelwood Road construction
Maintenance Crew:
Edge Break repairs MR52
Sealing shoulder – Kangaloolah Road
Premixing Regionals Roads
Concrete/Bridge Crew and Drainage Crew:
Kangaloolah Road drainage repairs and new pipes Middle Arm Road
Maintenance Grading Crew:
Flowerburn Road
Middle Creek Road
Woodhouslee Road
McAlister Road
Cummins Road
Peelwood Road
Ladevale Road
Iron Mines Road
Berrebangalo Road
Hillgrove Road – Maintenance grading.
If time permits move plant to Bevendale area to commence grading.
Major Works:
MR54 – Natural disaster drainage remediation works. (Crookwell to Goulburn)
MR54 – Signage upgrade – Junction point, Tuena Creek near the “Doll’s House”
- Resealing – programed to start on the 26th February near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek road.
- Wombat Crossing (TfNSW Project) – Goulburn St Crookwell Including line marking and 40km/h speed reduction of (HPAA) from Colyer to Roberts Street.
- Resealing – programed to start on the 19th February near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek road.
MR54 – Maintenance crew –
- Drainage works near James Park Rd and Abercrombie River Bridge.
- Continue to attend to priority maintenance issues as they arise.