Works update – 19 June 2023

23-06-2023

The following are roadworks commenced, completed or continued in the week ending 9 June, and those scheduled for the week ending 16 June 2023.

Week ending 16 June 2023

CONSTRUCTION CREW
Rugby Road – Gravel resheet
Laggan Road – Reconstruction. Roadworks sealed first section of Laggan Road Fri 16 June
Golspie Road – Rehabilitation and traffic control. Divalls sealed Golspie Road Thu 15 and Fri 16 June.

MAINTENANCE CREW
Ladevale Road – Culvert repairs & tar patching.
Dalton/Jerrawa Road – Tar Patching
Gundaroo Street, Gunning – Erect “T” intersection sign and raise “Termination Board” sign.

CONCRETE/BRIDGE CREW
Laggan Road – Installing stormwater pipe line.

DRAINAGE CREW
Laggan Road – Kerb and gutter prep and stormwater line.

GUNNING SHOWGROUND
Framing for new amenities block underway.

Proposed activities for week ending 23 June 2023

CONSTRUCTION CREW
Rugby Rd – Culvert Replacement, Drainage & Maintenance Grading
Goulburn Road – Guide posting and drainage Golspie Rd and heavy patch
Laggan Road – Reconstruction from 50km signs into Crookwell  

MAINTENANCE GRADING CREW
Bialla Road, Bulley’s Crossing Road & Heffernan’s Lane – Maintenance grading

MAINTENANCE CREW
Ladevale Road, Elms Road – Causeway repairs
Dalton / Jerrawa Road – Tar patching

CONCRETE/BRIDGE CREW
Carrington Street – Stormwater pipes and footpath

DRAINAGE CREW
Laggan Road – Kerb and gutter prep works and s/water pipes Laggan Road

BURRA BURRA BRIDHE REPLACEMENT

Bridge to be sealed, weather pending.