Works update – 2 February 2024

08-02-2024

The following are roadworks commenced, completed or continued in the week ending 2 February 2024, and those which were scheduled for the week ending 9 February 2024.

Week ending Friday 2 February 2024:

Construction Crew: Dalton Rd Rehab – Shoulder widening, roadside drainage and culvert replacement.

Maintenance Grading Crew: MR241, Little Plains Rd – Maintenance grading & maintenance gravel patching.

Maintenance Crew: Due to staff absences, crew was folded into construction crew for the week on Dalton Rd Rehab.

Week ending Friday 9 February 2024:

Construction crews:

Gravel re sheeting Currans Road and final trimming Court Street and Church Street, Taralga

Maintenance grading Saphire Road and final trimming Wheeo Road 

Dalton Road Rehab – Shoulder widening, culvert replacement & roadside drainage.

Maintenance Crew:

Dalton/Jerrawa Road – Roadside drainage.

Breadalbane Road – Tar Patching.

MR54 – Crack sealing Sunday evening – night 4/2/2024 in preparation for upgraded linemarking. Continue to attend to priority maintenance issues as they arise. 

Drainage & Concrete crew:

Drainage maintenance on various roads

Maintenance Grading Crew:

MR241 – Maintenance grading & maintenance gravel patching.

Major Works:

MR54 – Natural disaster drainage remediation works. (Crookwell to Goulburn)

  • Works started on 29th January between Alison Hone Reserve and Woodhouselee Road.
  • The road will be closed in one direction with speed restrictions in place during the day until 15th February.

MR54 – Upcoming works

  • Signage upgrade – Junction point, Tuena Creek near the “Doll’s House”
  • Roundabout Asphalting – Spring Street x Goulburn Street
  • Wombat Crossing (TfNSW Project) – Goulburn Street Crookwell Including linemarking and 40km/h speed reduction of (HPAA) from Colyer to Roberts Street.
  • Resealing – near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek Road.

Contractor Works:

  • Heavy Patching on MR248W Boorowa Road and MR52 Gundaroo Road to address bad patches for road safety.
  • Resealing continuing/nearing completion on Cullerin Road