Works update – 27 March 2023

29-03-2023

The following are some of the roadworks commenced, completed or continued in the week ending 24 March, and those scheduled for the week ending 31 March 2023.

Week ending 24 March 2023

CONSTRUCTION CREW
MR54 – Heavy Patching.
Reids Flat Road – Final trimming for seal.
Grabine Road – approaches at Sandy Creek culverts.
Gravelling Wheeo Road for rehab.

MAINTENANCE GRADING CREW
Maryvale Road – maintenance grading.

MAINTENANCE CREW
Bell’s Pit – access ramp & fencing.
MR241 – cleaning culverts.
Ladevale Road – bog hole repairs.

CONCRETE CREW
Woodville Road – completed concrete causeway.
Jerrong Road – installed new pipes.

DRAINAGE CREW
Laggan Road – Installing pipes and drainage works for rehab.

Proposed activities for week ending 31 March 2023

CONSTRUCTION CREW
MR54 – heavy patching.
Wheeo Road – gravelling for rehab.
Grabine Road – gravelling approaches to Sandy Creek culverts

MAINTENANCE GRADING CREW
Maryvale Road, Gullen Flats Road, Bannister Lane – maintenance grading.

MAINTENANCE CREW
MR241 – drainage.

CONCRETE CREW
Laggan Road – installing pits and lentals for rehab.

DRAINAGE CREW
Laggan Road – installing pipes for rehab.