The following are roadworks commenced, completed or continued in the week ending 24 November, and those which were scheduled for the week ending 1 December 2023.
Week ending Fri 24 November 2023:
Construction Crew:
MR241 REHAB
- Vegetation control completed
- Earthworks and clearing completed on first 1km
- Culverts completed on first 1km
- Started spreading and compacting gravel
Maintenance Crew:
- Pot hole pairs and edge breaks to Bannister Lane, MR52 South and Gurrundah Road
- Temporary culvert extension and headwall, Gurrundah Road
Week ending Fri 1 December 2023:
Construction crew:
- Wheeo Road
- MR54 Patches
- Repairs to Court Street Taralga
- Drainage Works – Brayton Road
- MR54 Pipe Upgrade – Tuena
Maintenance Crew:
- Minor Patching Bigga Road
- Premixing Several Shire/Regional Roads
- Sign replacement
- Cullerin
- Old Sydney Rd
- Mutmutbilly
- Fish River
Maintenance Grading Crew
- Fullerton Road
- Foggs Crossing Road
- MR 241
- Carnells Lane
- Coolalie Road
Major projects
MR54 – Works are almost complete on the Natural Disaster / Slip area North of Tuena.
- Earthworks, SO kerb and hydro-mulching works were completed on Friday 10th November.
- Asphalting was completed on Tuesday 14th.
- Guardrail was completed Wednesday 22nd
- The road is now open in both directions with speed restrictions removed.
MR54 – Drainage natural disaster remediation works move to near James Park road and will be completed on Monday 27th November.
MR54 – Heavy patching commenced between Alison Hone Reserve and Woodhouselee Road the Week of the 20th November. The works will continue this week, weather dependant, with 1 lane closed during the day for these important works to be completed.
MR54 – Drainage natural disaster remediation works between Sooley Creek and Pejar dam are programed to commence on Monday 4th December. The works will take approximately 1 week, with 1 lane closed during the day only for these works to be completed.
MR54 – Culvert replacement of 2 pipelines in Tuena Village is programed to start on Monday 4th December. The works will take approximately 2 weeks, with 1 lane closed during the day only for these works to be completed.
MR54 – Maintenance crew continue to attend to priority maintenance issues as they arise.