Works Update – 3 July 2023

13-07-2023

The following are roadworks commenced, completed or continued in the week ending 30 June, and those scheduled for the week ending 7 July 2023.

Week ending 30 June 2023

CONSTRUCTION CREW –

Rugby Rd – Drainage maintenance & culvert replacement.

Oolong Rd, Carnell’s Lane, Greendale Rd, Felled Timber Rd – Maintenance Grading.

MAINTENANCE GRADING CREW –

Heffernan’s Lane, Sapphire Rd – Maintenance grading.

MAINTENANCE CREW –

Elm’s Rd – Causeway repairs, drainage maintenance, roadside growth control.

Rugby Rd, Rye Park Rd – Tar Patching.

CONSTRUCTION CREW –

Laggan Road, Reconstruction Milling out and replacing the gravel from 50kph signs into Crookwell.

Middle Arm Road, Gravel re-sheeting sections most in need to gravel.

Concrete / Bridge Crew –

Carrington Street footpath is on hold due to staff on Annual Leave extra staff helping on Laggan Road drainage.

Drainage Crew –

Laggan Road, Kerb and gutter prep and stormwater line

Proposed activities for week ending 7 July 2023

Rugby Rd – Drainage maintenance, roadside growth control, storm damage repairs.

Rye Park Rd – Maintenance Grading.

MAINTENANCE GRADING CREW –

Sapphire Rd, Abby Collins’ Rd – Maintenance grading.

MAINTENANCE CREW –

Collector Rd – Drainage Maintenance.

Gurrundah Rd, Dalton/Jerrawa Rd – Tar patching.

Construction crew –

Middle Arm Road, Gravel re sheeting.

Construction crew –

Laggan Road, reconstruction on hold due to staff on Annual Leave extra staff are assisting in other areas.

Concrete/bridge crew –

Laggan Road, Carrington Street footpath on hold extra staff helping with stormwater drainage

Drainage crew –

Kerb and gutter back filling and placing lintels over pits