15-02-2024
The following are roadworks commenced, completed or continued in the week ending 9 February 2024, and those which were scheduled for the week ending 15 February 2024.
Week ending Friday 9 February 2024:
Construction Crew:
Dalton Road Rehab – Shoulder widening, roadside drainage and culvert replacements.
Maintenance Grading Crew:
MR241 – Maintenance grading and maintenance gravel patching.
Maintenance Crew:
MR241, Gurrundah Road & Old South Road – Tar patching.
Sheldrick’s Lane – Roadside drainage and maintenance gravel patching.
Week ending Friday 15 February 2024:
Construction crews:
Dalton Road Rehab – Culvert replacement, roadside drainage & shoulder gravelling.
Maintenance Crew:
Sheldrick’s Lane – Roadside drainage.
Jerrawa Rd, Braeadalbane Rd – Tar patching
Maintenance Grading Crew:
MR241 – Maintenance grading
Ladevale area – Maintenance grading.
Major Works:
MR54 – Natural disaster drainage remediation works. (Crookwell to Goulburn)
- Works between Alison Hone Reserve and Woodhouselee Road.
- One lane will be closed on the 14th February to seal the remediation works. Speed restrictions will be in place during the day. ( Weather dependant)
MR54 – Upcoming works
- Signage upgrade – Junction point, Tuena Creek near the “Doll’s House”
- Wombat Crossing (TfNSW Project) – Goulburn St Crookwell Including line marking and 40km/h speed reduction of (HPAA) from Colyer to Roberts Street.
- Resealing – programed to start on the 19th February near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek road.
MR54 – Maintenance crew – Preparation works for the upcoming resealing.
– Continue to attend to priority maintenance issues as they arise.