Works update – 6 March 2023

09-03-2023

The following are roadworks commenced, completed or continued in the week ending 3 March, and those scheduled for the week ending 10 March 2023.

Week ending 3 March 2023

CONSTRUCTION CREW
Dalton/Jerrawa Road Rehab – Roadside clearing & earthworks.

MAINTENANCE GRADING CREW
Wheeo Road – Maintenance Grading.

MAINTENANCE CREW
Collector Road – Drainage.
Walsh’s Road – Erect Depth Gauge sign on causeway.
Shire Roads – Drainage.

Proposed activities for week ending 10 March 2023

CONSTRUCTION CREW
Dalton/Jerrawa Road Rehab – Earthworks & drainage.

MAINTENANCE GRADING CREW
Aubynvale Road, Rugby Road (MR248 West to Bevendale), Redlands Road – Maintenance grading.

MAINTENANCE CREW
Sheldrick’s Lane, Coolalie Road, MR241 – Drainage.