The following are roadworks commenced, completed or continued in the week ending 29 February 2024, and those scheduled for the week ending 8 March 2024.

Week ending Friday 1 March 2024:

Construction Crew:

            Dalton Road Rehab – Gravelling

Woodhouselee Road rehabilitation and drainage

Peelwood Road rehabilitation

Maintenance Grading Crew:

            Hillgrove Road, Sapphire Rd

Maintenance Crew:

Gunning Streets, MR241 – Removing fallen trees.

MR241 – Fencing for drainage repairs

Sapphire Road – Tar patching

            Chain O’ Ponds Road, Carnell’s Lane, Dalton Streets – Clear drainage structures

Concrete/Bridge Crew and Drainage Crew:

Peelwood Road installing pipes and drainage

Proposed works week ending Friday 8 March 2024:

Construction crews:

Dalton Road Rehab – Gravelling

Woodhouselee Road rehabilitation

Peelwood Road rehabilitation

Maintenance Crew:

Minor repairs to Wombeyan Caves Road

Sapphire Roadd, Biala Rd, Abbey Collins’ Rd – Maintenance Grading

            Concrete/Bridge Crew and Drainage Crew:

Maintenance Grading Crew:

Leighwood Road

Yalbraith Road

Rhyanna Road

Carnell’s Lane – Culvert repairs

MR241 – Storm damage restoration to drainage structures.

Major Works:

MR54 – Natural disaster drainage remediation works. (Crookwell to Goulburn)

MR54 – Signage upgrade – Junction point, Tuena Creek near the “Doll’s House”

  • Resealing – programed to start on the 26th February near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek road.

MR54 – Maintenance crew –

  • Drainage works near James Park Road and Abercrombie River Bridge.