Works update – 20 June 2025

16-06-2025

The following are roadworks commenced, completed or continued in the week ending 20 June 2025

Week ending 20 June 2025

Construction Crew:

  • Julong Road, Crookwell River Bridge approaches and timber bridge removed.
  • Wheeo Road rehabilitation and sealing works completed.
  • MR54 Seg 330 (Binda Road). Major works are on hold until September. Bitumen sealing at Rylstone Road intersection planned, weather permitting. Hydro mulching planned for the coming fortnight.  
  • Sapphire Road Pavement Rehabilitation underway.  
  • Fish River Rd Gravel Resheeting underway.

Maintenance Grading Crew:

  • Maintenance Grading – Sapling Creek Road, Mulgowrie Roa completed.
  • Tyrl Tyrl Road – Upcoming
  • Woodhouselee Road
  • Carrabungla Road
  • Middle Arm Road
  • Rhyanna Road
  • Wheeo Road
  • Bevendale Road
  • Bertalba Road
  • Rye Park Road 

Maintenance Crew:

  • Potholing Wombeyan Caves Road  
  • Sealing urban patches 
  • Repairs to Gurrundah Rd Bridge  
  • Lost River Rd Drainage/Pipe Installation 
  • Urban Footpath Repairs/Maintenance 
  • Gravel Patching Abby Collins Road