Works update – 24 April 2023

26-04-2023

The following are roadworks commenced, completed or continued in the week ending 21 April, and those scheduled for the week ending 28 April 2023.

Week ending 21 April 2023

CONSTRUCTION CREW
Dalton /Jerrawa Road – Rehabilitation, gravelling.
Wheeo Road final trimming for seal and earthworks on next section
Grabine Road final trimming for seal and traffic control

MAINTENANCE GRADING CREW
Leary’s Lane, Storrier’s Lane, Walkom’s Lane – Maintenance grading.
Bialla Road – Tar Patching.

MAINTENANCE CREW
Mullin’s Creek Road – Tar patching.
Bell’s Pit – Fencing.
Dalton/Jerrawa Road Rehab – Driveways.
Felled Timber Road, Dalton Streets – Maintenance gravel patching.

CONCRETE CREW
Wheeo Road – Installing pipes and pipe extensions
Carrington Street – prep work for footpath

DRAINAGE CREW
Clifton Street & Laggan Road – Prep work for new kerb and gutter

Proposed activities for week ending 28 April 2023

CONSTRUCTION CREW
Dalton/Jerrawa Road – Rehabilitation, gravelling and seal preparation.
Golspie Road – Overlay and rehab
Wheeo Road – Earthworks and rehab

MAINTENANCE GRADING CREW
Pomeroy Road, Shaws Road – Maintenance grading.

MAINTENANCE CREW
Bialla Road, Cullerin Road, Mullin’s Creek Road, Old South Road – Tar patching.

CONCRETE CREW
Carrington St – Footpath