Works update – 1 May 2023

03-05-2023

The following are roadworks commenced, completed or continued in the week ending 28 April, and those scheduled for the week ending 5 May 2023.

Week ending 28 April 2023

CONSTRUCTION CREW
Dalton/Jerrawa Road Rehab – Seal preparation
Golspie Road rehab and overlay
Wheeo Road earthworks stage 2

MAINTENANCE GRADING CREW
Pomeroy Road – Maintenance grading

MAINTENANCE CREW
Gunning Streets, Biala Road – Tar patching

CONCRETE CREW
Carrington Street footpath in Apex Park

GUNNING ANZAC DAY CEREMONY – TRAFFIC CONTROL

Proposed activities for week ending 5 May 2023

CONSTRUCTION CREW
Dalton/Jerrawa Road – Seal preparation & signage
MR241 – Maintenance grading
Golspie Road rehab and overlay
Wheeo Road earthworks stage 2

MAINTENANCE GRADING CREW

Shaw’s Road, Birroon Road, Alton Hill Road, Clancy’s Road – Maintenance grading

MAINTENANCE CREW
Gurrundah Rd – Tar patching

CONCRETE CREW
Carrington Street footpath in Apex Park

DRAINAGE CREW
Laggan Road kerb and gutter preparation work