The following are roadworks commenced, completed or continued in the week ending 26 May, and those scheduled for the week ending 2 June 2023.

Week ending 26 May 2023

CONSTRUCTION CREW

Maryvale Road – Drainage
Felled Timber Road – Causeway repairs
Felled Timber Road, Rugby Road – Maintenance grading
Laggan Road – Reconstruction
Golspie Road – Rehab drainage and access pipes

MAINTENANCE GRADING CREW

Peelwood Road
Slaters Road – Gravel resheet
Redground Road – Gravel resheet
Redground Heights Road – Gravel resheet

MAINTENANCE CREW

Collector Road, Breadalbane Road, MR241, Old South Road, Boobalaga Road, Laggan-Taralga Road, Taralga-Oberon Road – Tar patching
Greendale Road, Offley’s Lane – Roadside clearing
Puckett’s Lane – Gravel patching & Drainage
Slaters Road –Drainage works

CONCRETE BRIDGE CREW

Carrington Street – Footpath down Northcott Street

DRAINAGE CREW

Laggan Road – Kerb and gutter preparation

Proposed activities for week ending 2 June 2023

CONSTRUCTION CREW

Rugby Road – Maintenance grading
Golspie Rd rehab access pipes and gravelling
Laggan Road – Reconstruction

MAINTENANCE GRADING CREW

Bialla Road, Bulley’s Crossing Road, Sapphire Road – Maintenance grading
Montana Road – Maintenance grading
Cooksvale Road – Maintenance grading
Mt Costigan Road – Maintenance grading
Redground Heights – Resheeting

MAINTENANCE CREW

Puckett’s Lane – Drainage
Sapphire Road, Old South Road, Mullin’s Creek Road, Breadalbane Road – Tar patching
Bigga Road, Grabine Road, Goulburn-Taralga Rd, Taralga-Oberon Road – Tar Patching
Slaters Road, Diamond Road – Drainage

CONCRETE/BRIDGE CREW

Carrington Street – Footpath

DRAINAGE CREW

Laggan Road –Kerb and gutter prep works Laggan Road

BUILDING WORKS

Replacement of the Gunning Showground Amenities is progressing, the old building is down and foundations have started for the new building.
Replacement of the timber bridge over Burra Burra on Blue Hills is waiting for some clear weather for a final seal.