The following are roadworks commenced, completed or continued in the week ending 2 June, and those scheduled for the week ending 9 June 2023.
Week ending 2 June 2023
CONSTRUCTION CREW
Golspie Rd – Rehabilitation access pipes and gravelling
Laggan Road – Reconstruction milling out material and replacing
CONCRETE/BRIDGE CREW
Carrington St – Continuing work on footpath
DRAINAGE CREW
Laggan Road – Kerb and gutter prep works
Proposed activities for week ending 9 June 2023
CONSTRUCTION CREW
Golspie Road – Trimming up for seal and driveway pipes
Laggan Road – Reconstruction trimming up to finished height
CONCRETE/BRIDGE CREW
Laggan Road – Installing drainage pits
DRAINAGE CREW
Laggan Road – Back filling kerb and gutter and starting storm water pipes