08-03-2024
The following are roadworks commenced, completed or continued in the week ending 29 February 2024, and those scheduled for the week ending 8 March 2024.
Week ending Friday 1 March 2024:
Construction Crew:
Dalton Road Rehab – Gravelling
Woodhouselee Road rehabilitation and drainage
Peelwood Road rehabilitation
Maintenance Grading Crew:
Hillgrove Road, Sapphire Rd
Maintenance Crew:
Gunning Streets, MR241 – Removing fallen trees.
MR241 – Fencing for drainage repairs
Sapphire Road – Tar patching
Chain O’ Ponds Road, Carnell’s Lane, Dalton Streets – Clear drainage structures
Concrete/Bridge Crew and Drainage Crew:
Peelwood Road installing pipes and drainage
Proposed works week ending Friday 8 March 2024:
Construction crews:
Dalton Road Rehab – Gravelling
Woodhouselee Road rehabilitation
Peelwood Road rehabilitation
Maintenance Crew:
Minor repairs to Wombeyan Caves Road
Sapphire Roadd, Biala Rd, Abbey Collins’ Rd – Maintenance Grading
Concrete/Bridge Crew and Drainage Crew:
Maintenance Grading Crew:
Leighwood Road
Yalbraith Road
Rhyanna Road
Carnell’s Lane – Culvert repairs
MR241 – Storm damage restoration to drainage structures.
Major Works:
MR54 – Natural disaster drainage remediation works. (Crookwell to Goulburn)
MR54 – Signage upgrade – Junction point, Tuena Creek near the “Doll’s House”
- Resealing – programed to start on the 26th February near these locations, Alison Hone Reserve, Pejar Dam, Wades Hill and Bridge Creek road.
MR54 – Maintenance crew –
- Drainage works near James Park Road and Abercrombie River Bridge.
- Continue to attend to priority maintenance issues as they arise.