The following is a list of commenced and completed roadworks for the weeks beginning 2 January and 9 January 2023.
Work commenced or completed 3 January 2023:
- Maintenance grading team – maintenance grading Mares Forest Road and Guineacor North Road.
- Maintenance team – Pot holing MR 248 Boorowa Road from Lost River Road towards the boundary.
- Float driver – moving plant to different road locations for teams to be able to start work next week.
- Maintenance Crew have undertaken hand tar patching work on the following roads – Dalton/Jerrawa Rd, Cook’s Hill Rd, MR241, Collector Rd and Gunning Streets.
- Construction Crew have erected “Chevron” and Speed Limit Signs on the Friar’s Hill Rehab on Gurrundah Rd.
Work starting 9 January:
- Maintenance grading team – maintenance grading Mares Forest Road.
- Maintenance grading team – Gravel re sheeting Glenerin Road.
- Construction team – Gravel re sheeting Mulgowrie Road and preparing a section for sealing.
- Maintenance team – gravel pot holing various roads.
- Construction Crew – Replacement of damaged stormwater covers in Gunning Streets.
- Collector Rd – Gravelling of storm damaged section.
- Maintenance Crew – Erection of Depth Gauge signs on Catherine’s Creek. causeway on Flacknell Creek Rd, erection of Depth Gauges on Balkney Creek Causeway on MR241.
- Laying of gabion rock at Blakney Creek causeway on MR241 to assist in delineation of damaged causeway.
- Bog excavation and rehabilitation on Blakney Creek Rd South.
- Maintenance Grading Crew – Grading of Flacknell Creek Rd, MR241, Pudman Creek Rd.